Zoned Out: AI Data Centers Meet Local Land & Water Law

Big Bets, Small Boards
Most conversations about AI come back to scale: bigger models, more chips, more computing power. Less often discussed is where all of that computing actually lives. Behind every chatbot is a data center, and behind every data center is a plot of land, a connection to the grid, and a water supply that someone local has to approve.
In California's Imperial Valley, that approval process has ended up in court. The developer behind a planned AI data center there originally intended to cool it with recycled water from neighboring cities. When that plan fell through, it turned to the Colorado River instead, and in June it sued for access to 260 million gallons of river water a year.
The dispute reflects a broader challenge facing the AI buildout. Tech companies and their investors are lining up more than $6 trillion in AI spending through 2030, and all of that compute has to physically sit somewhere, plugged into a local grid and drawing from a local water supply. That puts some of the biggest bets in tech in front of city councils, planning commissions, and irrigation districts, many of which are pushing back. According to Data Center Watch, local opposition blocked or delayed at least 75 data center projects worth about $130 billion in the first quarter of 2026, roughly matching all of 2025. Another 45 projects worth nearly $68 billion faced the same in the next quarter.
Zoning: Lost in the Code
Most local zoning codes were written long before hyperscale data centers existed, and that gap has turned out to matter. New Orleans found this out in January 2026, when a developer sought to rezone vacant residential land in New Orleans East for a data center. The city's code did not define "data center" at all, so a project could potentially apply under a different use, such as office space with computers. The City Council responded with a one-year interim zoning district banning new data centers while planners came up with a definition. The developer pulled its permit within hours. City planning staff have since recommended a citywide ban on large and hyperscale facilities.
The legal challenge begins with how zoning ordinances classify land use. Local governments generally divide land into residential, commercial, and industrial zones, each with rules governing what can be built. Data centers do not always fit neatly into these categories. Although they may resemble office buildings, their extensive electrical equipment, cooling systems, and infrastructure needs can make them function more like industrial facilities. Without a clear classification, developers may face uncertainty over whether their projects are permitted under existing zoning laws or require additional approvals.
That uncertainty can create problems before construction even begins. Developers may purchase land, secure financing, and begin the permitting process only to encounter new restrictions or conflicting interpretations of local zoning rules. A project that initially appears permissible could suddenly require rezoning, a special-use permit, or changes to its proposed design. For developers and investors, these complications can increase costs and delay construction, making zoning compliance an important consideration when evaluating potential data center sites.
The New Orleans dispute reflects a broader challenge as AI infrastructure expands faster than the regulations governing it. Local governments must determine how to accommodate new facilities while addressing concerns about electricity demand, water consumption, and surrounding communities. Meanwhile, developers need clear and predictable rules to make long-term investments.
Water Rights: Thirsty for Approval
Data centers need water for cooling, and many are proposed in places where water is already scarce. The Imperial Valley dispute shows how quickly that becomes a legal question. The developer, Imperial Valley Computer Manufacturing (IVCM), is planning a 330-megawatt campus that would need roughly 750,000 gallons of water a day. When the Imperial Irrigation District (IID) denied its application for industrial water service, the company asked a court to step in.
Initially, IVCM planned to avoid drawing additional water from the drought-stressed Colorado River by purchasing treated wastewater from the cities of Imperial and El Centro. The company offered to fund upgrades to municipal wastewater treatment facilities and spend millions of dollars purchasing recycled wastewater. However, according to IVCM’s lawsuit, both cities withdrew from negotiations, leaving the company without its intended water supply.
After these agreements fell through, IVCM pursued an alternative strategy. They leased 160 acres of agricultural land, taking it out of production, and attempted to redirect the land’s historical water allocation to the data center. The company argued that because the farmland historically consumed approximately the same amount required by the data center, retiring it from agricultural production would allow that water to support industrial cooling without increasing overall water demand.
Despite IVCM’s proposed alternative, IID denied its industrial water service application on May 1, 2026. The central legal issue is whether leasing farmland with an existing water allocation gives a developer the right to transfer the water to industrial use. IID must consider its water-service policies, infrastructure capacity, and legal obligations before applying such a transfer. IVCM, meanwhile, argues that IID has a duty to provide water service fairly and cannot arbitrarily deny its application, prompting the company to challenge the decision in court.
The lawsuit also exposes a broader conflict between Imperial County’s industrial development plans and existing water policies. The county’s Lithium Valley Specific Plan anticipates increased demand for water from lithium processing, manufacturing, and data centers. This is partly through redirecting water historically used for agriculture. However, IID’s Interim Water Supply Policy allocates only 18,620 acre-feet annually for new non-agricultural uses, while the county projects that industrial demand could exceed three times that amount within 20 years. This raises questions about whether existing water policies can accommodate the region’s planned industrial expansion.
Investor Risk: Force Majeure, Major Delays
The rapid expansion of AI infrastructure is exposing investors and lenders to growing financial risks as multibillion-dollar data center projects face uncertainty over construction timelines and profitability. In September 2026, Oracle issued a “force majeure” notice regarding Project Jupiter, a major AI data center in New Mexico backed by Blue Owl Capital, citing potential delays in securing electricity. According to Reuters, Blue Owl had invested about $3 billion in equity in the project, with higher returns expected once construction was complete. Any delay could postpone those returns while financing and development costs continue to add up.
The dispute highlights the importance of force majeure clauses in AI infrastructure agreements. These contractual clauses generally address circumstances beyond the parties’ control that prevent or delay performance. However, invoking force majeure does not automatically excuse a party from its contractual obligations. Whether the clause applies depends on the specific contract language and circumstances surrounding the delay. In Project Jupiter’s case, Oracle reportedly sought to preserve its ability to postpone certain payments if electricity shortages prevented the facility from opening on schedule in 2028. Meanwhile, Blue Owl maintained that the notice did not change the parties’ financial commitments.
The financial consequences extend beyond just the immediate parties. Large AI data centers often depend on substantial outside financing, making construction schedules and anticipated revenue important considerations for lenders. When projects encounter delays in securing electricity, investors may face longer periods before receiving expected returns, while lenders must evaluate whether existing contractual protections adequately address those risks. Project Jupiter illustrates how infrastructure constraints can create financial uncertainty even when demand for AI computing is strong.
As investment in AI infrastructure continues to grow, these concerns may influence how future financing and development agreements allocate responsibility for construction delays, electricity shortages, and unexpected costs. The Project Jupiter dispute shows the importance of clearly defining contractual obligations and allocating financial risks as developers and investors navigate the challenges of expanding AI infrastructure.
Breaking Ground, or Not
Each of these disputes leaves a legal question unsettled. New Orleans must define a data center before deciding where one belongs, the Imperial Valley case will test whether farm water can be shifted to industrial use, and Project Jupiter shows the limits of force majeure when power depends on state approvals. The answers will shape how AI deals are structured, from when developers secure zoning and water to who pays when approvals run late. For an industry focused on how fast it can build, the more pressing question may be how long it has to wait.